Welcome to the official website of Guangdong  Dedi Mechanical And Electrical Equipment Co., Ltd!

 Tel:0758-6663288       E-mail:2823802733@qq.com

图片展示
图片展示

Reactive power compensation device debugging

Author:广东德帝机电有限公司 Click: Time:2018-01-02 00:00:00

The debugging content of the static reactive power compensation device composed of power capacitors includes: (1) routine inspection and testing of capacitors and switchgear. (2) Manual and automatic switching program test for capacitors. When checking the automatic switching program of capacitors, it is necessary to provide test signals at the current and voltage input terminals of the switching controller, adjust the phase difference between the two signals, simulate changes in the power factor of the power grid, confirm the switching action of capacitor connection and exit, measure the power factor value of the switching point and the hierarchical switching delay time, and adjust relevant parameters according to the design. (3) Closing operation test. The content includes: impact closing test; Measurement of each phase current of capacitor bank and determination of current difference; Measure the power factor and grid voltage of the compensated power grid system during no-load and full load operation, and provide evaluation data on the effectiveness of reactive power compensation, capacitor configuration, and the tap position (or on load voltage regulation) of the main power transformer.

Dynamic and reactive power compensation devices are designed to meet the requirements of large steel rolling mills and other equipment with high reactive power impact loads, which can be quickly compensated. The debugging content mainly includes: (1) individual inspection and testing of capacitors, reactors with adjustable inductance, switchgear, thyristor control and regulation devices, as well as testing and setting of protective relays. (2) Test the action program of each circuit breaker, switch, and main power transformer on load voltage regulating device. (3) Simulation testing and adjustment of the automatic voltage regulation characteristics of the on load voltage regulation device of the main power transformer. (4) Measurement of resonance frequency of filtering circuit. When there is a significant deviation from the design value, the reactor tap can be adjusted. (5) Adjustment of the cooling water system. (6) Trial operation and dynamic debugging. Input cooling water, on load voltage regulation, and reactive power compensation monitoring systems. After confirming normal operation, input reactive power regulation devices and measure signal waveforms at each testing point; Starting from the low order, input a set of filtering circuits each time, and determine the correspondence between the reactive power regulation capacity and the filtering circuit capacity; Measure the resonance parameters of the filtering circuit using a harmonic analyzer, and record the output voltage waveform of the system voltage transformer with an oscilloscope at this time, which should be free of distortion and oscillation; All filters are put into operation and subjected to the same tests as above, and there should be no abnormal phenomena such as parallel resonance. (7) Debugging when inputting impact loads. The oscillographic recording system records the changes in parameters such as the output ratio, grid voltage, and power factor of the reactive power compensation device when operating under shock loads (such as biting and throwing steel in the rolling mill), and records the response characteristic curve of dynamic adjustment; Adjust the relevant parameters in the system (such as the time constant of the reactive power regulator) to achieve the best dynamic reactive power compensation effect.

图片展示

About | Product | Equipment |Case | News

图片展示

微信公众号

图片展示

微信小程序

CONTACT US


Tel:0758-6663288

Fax:0758-6663288-828

E-mail:2823802733@qq.com

Add:201, 2nd Floor, Building 8, Yingtian Zhigu Industrial Park, Pingfeng Expansion Zone, Guangdong Guangxi Cooperation Special Experimental Zone, Pingfeng Town, Fengkai County, Zhaoqing City, Guangdong Province

Copyright@ Guangdong  Dedi Mechanical And Electrical Equipment Co., Ltd  All Right Reserved       ICP: 粤ICP备15100755号-1            粤公网安备 44060602000701号

Copyright@ Guangdong  Dedi Mechanical And Electrical Equipment Co., Ltd  All Right Reserved       ICP: 粤ICP备15100755号-1            粤公网安备 44060602000701号

 

Service Center
Contacts
Qrcode
Top
Service Center
Contacts
热线电话
0758-6663288
上班时间
周一到周五
E-mail地址
2823802733@qq.com
Qrcode
Qrcode
扫码关注
Add WeChat friend to learn more about the product
Use Enterprise WeChat
"Scan" to join the group chat
Copy success!
Add WeChat friend to learn more about the product
I see.